implementation:manufacturing:po_extension

Differences

This shows you the differences between two versions of the page.

Link to this comparison view

Both sides previous revision Previous revision
implementation:manufacturing:po_extension [2017/12/05 15:46]
csuhaa missing link
implementation:manufacturing:po_extension [2018/03/22 12:10] (current)
csuhaa 18.1
Line 1: Line 1:
-======4. Production order======+======4.4. Production order======
 Production orders also inherit the Produmex Manufacturing extension settings from their base Bill of Materials. For production orders other extensions are available, including //​‘Milestone Groups’//,​ //‘Due Time’//, and //​‘Allocation Strategy’//​. Production orders also inherit the Produmex Manufacturing extension settings from their base Bill of Materials. For production orders other extensions are available, including //​‘Milestone Groups’//,​ //‘Due Time’//, and //​‘Allocation Strategy’//​.
  
-**//Milestone groups//** \\+=====4.4.1. Header and Grid ===== 
 +==== ==== 
 +{{section>​implementation:​manufacturing:​bom_extension#​row_type&​noeditbtn}} 
 + 
 +===Row Image=== 
 +Indicates the row type.  
 + 
 +|  {{ :​implementation:​manufacturing:​functional:​extensions:​material.png |material}} ​  ​| ​ raw material/subassembly material/supplier material ​  | 
 +|  {{ :​implementation:​manufacturing:​functional:​extensions:​operations_pro.png |}}  |  operation/fully outsourced operation/operation cannot be allocated/​finished | 
 +|  {{ :​implementation:​manufacturing:​functional:​extensions:​unfinished.png |unfinished}} ​ |  unfinished product/​unfinished material ​ | 
 +|  {{ :​implementation:​manufacturing:​functional:​extensions:​byp.png |by-product}} ​ |  by-product ​ | 
 +|  {{ :​implementation:​manufacturing:​functional:​extensions:​resphant.png |phantom item}} ​ |  phantom item  | 
 +|  {{ :​implementation:​manufacturing:​functional:​extensions:​cost.png |cost}} ​ |  cost  | 
 + 
 +//To see the Operation Details form, click on the Row Image of the operation.//​ 
 + 
 +{{section>​implementation:​manufacturing:​bom_extension#​milestone_type&​noeditbtn}} 
 + 
 +{{section>​implementation:​manufacturing:​bom_extension#​bxid&​noeditbtn}} 
 + 
 +{{section>​implementation:​manufacturing:​bom_extension#​rejected_warehouse&​noeditbtn}} 
 + 
 +===Milestone groups===
 Production orders inherit the milestone type from the base BoM. An additional ‘Milestone Group’ field is added to the production orders which contains the code of the operation the line belongs to. This field is automatically set by the add-on based on the milestone settings and it cannot be changed manually. Production orders inherit the milestone type from the base BoM. An additional ‘Milestone Group’ field is added to the production orders which contains the code of the operation the line belongs to. This field is automatically set by the add-on based on the milestone settings and it cannot be changed manually.
  
-**//Allocation error//** \\+===Allocation error===
 Operations with allocations errors are indicated with an   icon on the ‘Row Image’ field. Operations with allocations errors are indicated with an   icon on the ‘Row Image’ field.
  
-**//Due Date & Due Time//** \\+===Due Date & Due Time===
 After the production order is added/​updated,​ an advanced MRP runs in the background and calculates the due dates and times the operation must be finished/ the material must be available. After the production order is added/​updated,​ an advanced MRP runs in the background and calculates the due dates and times the operation must be finished/ the material must be available.
  
-**//Manual Planning//** \\+===Manual Planning===
 Defines whether this line is taken into account by the MRP logic or not. Defines whether this line is taken into account by the MRP logic or not.
  
-**//MRP result//** \\+===MRP result===
 On operation lines indicates whether there is an error with the allocation or not. On operation lines indicates whether there is an error with the allocation or not.
  
-**//MTO scenario//** \\+===MTO scenario===
 If the production order is a part of an MTO chain and its subassembly line has an MTO production order, the MTO scenario code is displayed on this field on the line of the subassembly. If the production order is a part of an MTO chain and its subassembly line has an MTO production order, the MTO scenario code is displayed on this field on the line of the subassembly.
  
-**//Operation Reference//** \\+===Operation Reference===
 In material lines it shows the BX ID of the linked operation. In operation lines it shows the BX ID of the next operation. In material lines it shows the BX ID of the linked operation. In operation lines it shows the BX ID of the next operation.
  
-**//Planned Outsourced Quantity//** \\+===Planned Outsourced Quantity===
 The planned outsourced quantity of an unfinished product. The planned outsourced quantity of an unfinished product.
  
-**//Completed Outsourced Quantity//** \\+===Completed Outsourced Quantity===
 The completed quantity of the unfinished product received from the subcontractor. The completed quantity of the unfinished product received from the subcontractor.
  
-**//Rejected Outsourced Quantity//** \\+===Rejected Outsourced Quantity===
 The quantity of an unfinished product that was booked as ‘Rejected’ by the quality inspector. The quantity of an unfinished product that was booked as ‘Rejected’ by the quality inspector.
  
-**//Completed Quantity//** \\+===Completed Quantity===
 The completed quantity booked with PDC for an operation. The completed quantity booked with PDC for an operation.
  
-**//Rejected Quantity//** \\+===Rejected Quantity===
 The quantity booked as ‘Rejected’ with PDC for an operation. The quantity booked as ‘Rejected’ with PDC for an operation.
  
-=====4.1. User Defined Fields===== +=====4.4.2. User Defined Fields===== 
-**//Allocation strategy//** \\+{{section>​implementation:​manufacturing:​bom_extension#​user_defined_fields&​noheader&​noeditbtn}} 
 + 
 +===Allocation strategy===
 On the ‘Allocation Strategy UDF’ the scheduling logic for allocations can be defined. The default the allocation strategy depends on the //​‘Default ProdOrd. Allocation Strategy’//​ set on the [[implementation:​manufacturing:​confguide#​production_order_tab|Production order tab]] of Produmex Manufacturing settings. On the ‘Allocation Strategy UDF’ the scheduling logic for allocations can be defined. The default the allocation strategy depends on the //​‘Default ProdOrd. Allocation Strategy’//​ set on the [[implementation:​manufacturing:​confguide#​production_order_tab|Production order tab]] of Produmex Manufacturing settings.
  
Line 51: Line 75:
 {{ :​implementation:​manufacturing:​functional:​extensions:​warning.png |System message}} {{ :​implementation:​manufacturing:​functional:​extensions:​warning.png |System message}}
  
-**//Due Time//** \\+===Due Time===
 Produmex Manufacturing extends the production order Due Date with a time component. With the Due Time production planning is detailed at the time of day level. Produmex Manufacturing extends the production order Due Date with a time component. With the Due Time production planning is detailed at the time of day level.
  
-**//Force Reallocation//** \\+===Force Reallocation===
 To recalculate the allocations for the production order, set the ‘Force Reallocation’ option to ‘Yes’ and click update. After the reallocation,​ the value will be set back to ‘No’. To recalculate the allocations for the production order, set the ‘Force Reallocation’ option to ‘Yes’ and click update. After the reallocation,​ the value will be set back to ‘No’.
  
Line 67: Line 91:
 Under the //​‘General’//​ category production comments, missing capacity information and MTO details are indicated. Under the //​‘General’//​ category production comments, missing capacity information and MTO details are indicated.
  
-=====4.2. Right-click menu ===== +=====4.4.3. Right-click menu ===== 
-====4.2.1. ​Allocation status====+===Allocation status===
 To see the list of allocation errors for the production order after the creation or an update, select the //​‘Allocation status’// option from the right-click menu. On the opening //‘System Message’//​ form allocation errors will be listed. To see the list of allocation errors for the production order after the creation or an update, select the //​‘Allocation status’// option from the right-click menu. On the opening //‘System Message’//​ form allocation errors will be listed.
  
 {{ :​implementation:​manufacturing:​functional:​extensions:​system_message_2.png |System message}} {{ :​implementation:​manufacturing:​functional:​extensions:​system_message_2.png |System message}}
  
-====4.2.2. ​Operations Sequence Diagram====+===Operations Sequence Diagram===
 To review the schedule/​planning/​allocations of a single production order, open the ‘Operations sequence diagram’ form. The form can be reached from the right-click menu of the production order. To review the schedule/​planning/​allocations of a single production order, open the ‘Operations sequence diagram’ form. The form can be reached from the right-click menu of the production order.
  
Line 82: Line 106:
 {{ :​implementation:​manufacturing:​functional:​extensions:​qs_operstion_seqdiagr.png |Operations Sequence Diagram}} {{ :​implementation:​manufacturing:​functional:​extensions:​qs_operstion_seqdiagr.png |Operations Sequence Diagram}}
  
-====4.2.3. ​Allocation Report====+===Allocation Report===
 After a production order has been created or updated, the Allocation/​calculations results report can be opened from the right click menu to overview the allocations. The red cog indicates an allocation error where the system could not allocate enough capacity for the operation. After a production order has been created or updated, the Allocation/​calculations results report can be opened from the right click menu to overview the allocations. The red cog indicates an allocation error where the system could not allocate enough capacity for the operation.
  
 {{ :​implementation:​manufacturing:​functional:​extensions:​allocation_reports.png |Allocation Report}} {{ :​implementation:​manufacturing:​functional:​extensions:​allocation_reports.png |Allocation Report}}
  
-====4.2.4. ​Job Requirements Report====+===Job Requirements Report===
 For more information please see: [[implementation:​manufacturing:​quickstart#​print_production_reports|Requirements Report]] For more information please see: [[implementation:​manufacturing:​quickstart#​print_production_reports|Requirements Report]]
  
-====4.2.5. ​Material Requirements Report====+===Material Requirements Report===
 For more information please see: [[implementation:​manufacturing:​quickstart#​print_production_reports[|Requirements Report]] For more information please see: [[implementation:​manufacturing:​quickstart#​print_production_reports[|Requirements Report]]
  
-====4.2.6. ​Missing Capacity Report====+===Missing Capacity Report===
 On the missing capacity report operations from the production order are listed if the total capacity needed for the operation is not available. Select a line and click on the ‘Job Scheduling Control Panel’ button to see the work center in question on the control panel. On the missing capacity report operations from the production order are listed if the total capacity needed for the operation is not available. Select a line and click on the ‘Job Scheduling Control Panel’ button to see the work center in question on the control panel.
  
 {{ :​implementation:​manufacturing:​functional:​extensions:​missing_cap_rep.png |Missing Capacity Report}} ​ {{ :​implementation:​manufacturing:​functional:​extensions:​missing_cap_rep.png |Missing Capacity Report}} ​
  
-====4.2.7. ​Resource Allocations====+===Resource Allocations===
 For more information please see: Resource Allocations. Please note: As ‘Planned’ production orders do not have permanent allocations,​ the allocation report is not available for ‘Planned’ production orders. ​ For more information please see: Resource Allocations. Please note: As ‘Planned’ production orders do not have permanent allocations,​ the allocation report is not available for ‘Planned’ production orders. ​
  
-====4.2.8. ​Job Scheduling Control Panel====+===Job Scheduling Control Panel===
 For more information please see: [[implementation:​manufacturing:​jscp|Job Scheduling Control Panel]] For more information please see: [[implementation:​manufacturing:​jscp|Job Scheduling Control Panel]]
  
-====4.2.9. ​Calculate Production Orders====+===Calculate Production Orders===
 For more information please see: [[implementation:​manufacturing:​costcalc#​calculating_production_orders|Cost calculation]] For more information please see: [[implementation:​manufacturing:​costcalc#​calculating_production_orders|Cost calculation]]
  
-====4.2.10. ​List of Calculated Production Orders====+===List of Calculated Production Orders===
 For more information please see: [[implementation:​manufacturing:​costcalc#​calculating_production_orders|Cost calculation]] For more information please see: [[implementation:​manufacturing:​costcalc#​calculating_production_orders|Cost calculation]]
  
-====4.2.11. ​MTO Planning====+===MTO Planning===
 For more information please see: [[implementation:​manufacturing:​maketo|MTO Planning]] For more information please see: [[implementation:​manufacturing:​maketo|MTO Planning]]
implementation/manufacturing/po_extension.txt · Last modified: 2018/03/22 12:10 by csuhaa