With default configurations only the work center dimension of the allocation is used in the MRP, therefore the other two dimensions cannot be displayed on the Job Scheduling Control Panel. To enable multidimension allocation, go to the MRP tab of the Produmex Manufacturing Settings and check the ‘Use multidimension allocation’ option.
To use the ‘Align allocations’ function for work centers, adjust the ‘JSCP align max days‘ and ‘JSCP align gap minutes’ options on the Prod. Order tab of Produmex Manufacturing Settings.
To allow the automatic rescheduling of production orders in the case of shift day capacity shrunk, enable the ‘Allow rescheduling Production Orders when shift day capacity is shrunk’ on the MRP tab of Produmex Manufacturing Settings. To enable the automatic align of child MTO orders, enable the ‘AutoRoll child MTOs’ option in the MTO tab of Produmex Manufacturing Settings.
(1) Work Centers: Use this button to show or hide work centers on the panel.
(2) Employees: Use this button to show or hide employees on the panel.
(3) Tools: Use this button to show or hide tools on the panel.
(4) Period: Select the time scale on the dropdown list. The possible values are:
(5) Query: On the opening form the parameters of the panel can be set.
(6) Filters: Add filters to the panel on the Filters form.
(7) Refresh: Click on the button to redraw the panel by reloading data from the database.
(8) Options: Click on the button to open the ‘Configurations’ form.
(9) Print: Set the printing options on the opening form.
(10) Feed to Management Cockpit: Click on the button to see the production orders linked to the displayed operations on the Production Management Cockpit.
(11) Timescale: Set the timescale for drag and drop. The following periods can be set: day, hour, half an hour, 20 minutes, 15 minutes, 10 minutes, 5 minutes, 1 minute. The Timescale setting defines how the start time of the dropped allocation is rounded.
(12) Undo/ Redo: Click on the left arrow to undo a drag&drop action. Click on the right arrow to redo an undone drag&drop action. After updating, the action cannot be undone. Only active if the 'Enable drag & drop in Job Scheduling Control Panel' option is enabled on Produmex Manufacturing Settings.
(13) MTO Scenario: Choose MTO Scenario from a list. The selected scenario will be highlighted.
Work Centers: Click on the gray arrow to expand or collapse the row of the work center.
From the right-click menu on work center row the following displaying options can be selected:
When there is a discrepancy on the MTO chain, an additional section is displayed on the bottom of the form. The scenario code, the work center in concern, the time and the error message is displayed on a table.
When an MTO chain is highlighted, the order sequence is visualized with arrows. When there is a discrepancy, the arrow is red, otherwise it is white. Double-click on the message to highlight the MTO scenario and to see the arrow showing the scheduling issue.