7. Move Components to the Production Line
You have the following options to move the picked components to the production line:
(1) If you produce with the Receipt from Production flow, the picked components can be moved to the production line with the Move to Production Line flow (see section 7.1 below).
(2) If you produce with the Production flow, you can use the Move to Production Line flow (see section 7.1 below) or you can move the components on the terminal (see 8.2.8. Move the components to the production line).
Note:
- When the Auto move all linked items to BOM? setting is enabled on the Production controller, the system automatically moves the components from the input location to the production line after selecting the production order in the Receipt from Production flow or Production flow.
- With default settings, components can only be moved from the input location to the production line. If the Allow to move stock to prod. line from rest location? setting is enabled on the Production controller, the components can also be moved from the rest location to the production line.
7.1. Move to Production Line flow
7.1.1. Start the flow
7.1.2. Select a production line
Select the production line on the Select a production line screen and tap the right arrow.
When there is no started production order on the selected line, the system displays the No started production order found message. Tap OK
and the system goes back to the Select a production line screen.
7.1.3. Select a production order
- If there is more than one started production order, the system displays the Select a production order to pick for screen.
Select a production order, tap the right arrow and the system displays the Production information screen. - If there is one started production order, the Select a production order to pick for screen is skipped and the Production information screen is displayed.
- The Production information screen displays the following information:
- Production order number
- Planned quantity
- The code, the description and the barcode of the item to produce
- The due date of the production order
- Remarks for the production order
- Tap
OK
.
7.1.4. Select an item to move
After identifying the production order, the system lists the components from the production order on the Items to move screen. Only those components are listed that are available on the input location.
Note: Time registry items are not displayed on the list.
Next to the item code the system displays the quantity to be moved. Negative quantity means that the quantity on the production line exceeds the planned quantity.
Select an item and tap the right arrow button.
7.1.5. Identify the SSCC to move
On the Identify the SSCC to move screen you have the following options:
- a) scan the SSCC to move (see section (a) below),
- b) move a partial logistic unit (see section (b) below),
- c) go back to the Select a production line screen by tapping the
Stop
button or the left arrow.
a) Scan the SSCC to move.
Note: Only SSCCs meeting the following conditions can be moved:
- there are items linked to the production order on the logistic unit,
- the logistic unit is stored on the input location of the production line.
When the SSCC is scanned and the logistic unit is moved to the production line, the system displays the Logistic unit/items are moved message. Tap OK
.
The movement is registered in the Produmex office module in a Move document.
If there are other items to move, the system displays the Identify the SSCC to move screen.
If there is no more item to move, the flow is finished, and the system displays the Select a production line screen.
b) Move a partial logistic unit.
- Tap the
Partial logistic unit
button. - On the Scan a product screen scan the product or tap the
Select a product
button and select the product from the displayed list. - Enter the number of items on the Enter the quantity screen and tap the right arrow.
Note: The moved quantity cannot exceed the available quantity on the input location, but it can exceed the planned quantity of the component on the production order.
The components are moved to the production line and the movement is registered in the Produmex office module in a Move document.
If there are other items to move, the system goes back to the Identify the SSCC to move screen.
If there is no more item to move, the flow is finished, and the system displays the Select a production line screen.